Project

General

Profile

Actions

Bug #2498

open

Timesheets (Non submitted - Flow ):- Unable to create the same project and same task with different statuses

Added by Anantha kumar 11 months ago. Updated about 1 month ago.

Status:
Feedback
Priority:
Normal
Assignee:
Start date:
04/12/2024
Due date:
% Done:

0%

Estimated time:

Description

Steps
1.Click on timesheets Menu.
2.Select Non submitted tab
3.Select the project Legal/General
4.Select consultations in task selection dropdown
5.Select the status as Billable
6.Enter all fields and save it
7.Again, create the same entry and change the status as non-billable and save it
8.Recently created the timesheet entry updated in the existing entry.
9.Unable to create same project and task with different status


Files

Different Task.mp4 (2.83 MB) Different Task.mp4 Anantha kumar, 11/25/2024 08:40 AM
Actions #1

Updated by Anantha kumar 11 months ago

  • Assignee set to Arun Sundar
Actions #2

Updated by Arun Sundar 7 months ago

  • Status changed from New to Resolved
Actions #3

Updated by Arun Sundar 7 months ago

  • Assignee changed from Arun Sundar to Anantha kumar
Actions #4

Updated by Anantha kumar 6 months ago

Try to create the same project, task with different status 'Billable or Non Billable'

Actions #5

Updated by Anantha kumar 3 months ago

The mentioned issue is not fixed, please refer the videos attached.

Actions #6

Updated by Arun Sundar 2 months ago

  • Status changed from New to Resolved
  • Assignee changed from Arun Sundar to Vengadeshwaran R
Actions #7

Updated by Arun Sundar 2 months ago

  • Status changed from Resolved to In Progress
  • Assignee changed from Vengadeshwaran R to Arun Sundar
Actions #8

Updated by Arun Sundar about 1 month ago

  • Status changed from In Progress to Feedback
  • Assignee changed from Arun Sundar to Anantha kumar

The same issue is replicated in IOS and WEB also. We are not able to create the same project, task with different status 'Billable or Non Billable'.

Actions

Also available in: Atom PDF