Timesheets (Non submitted - Flow ):- Unable to create the same project and same task with different statuses

Added by Ananth Kumar 9 months ago. Updated 15 days ago.

Status:
In Progress
Priority:
Normal
Assignee:
Start date:
04/12/2024
Due date:
% Done:

0%

Estimated time:

Description

Steps
1.Click on timesheets Menu.
2.Select Non submitted tab
3.Select the project Legal/General
4.Select consultations in task selection dropdown
5.Select the status as Billable
6.Enter all fields and save it
7.Again, create the same entry and change the status as non-billable and save it
8.Recently created the timesheet entry updated in the existing entry.
9.Unable to create same project and task with different status


Files

Different Task.mp4 (2.83 MB) Different Task.mp4 Ananth Kumar, 11/25/2024 08:40 AM
Actions #1

Updated by Ananth Kumar 9 months ago

  • Assignee set to Arun Sundar
Actions #2

Updated by Arun Sundar 5 months ago

  • Status changed from New to Resolved
Actions #3

Updated by Arun Sundar 5 months ago

  • Assignee changed from Arun Sundar to Ananth Kumar
Actions #4

Updated by Ananth Kumar 5 months ago

Try to create the same project, task with different status 'Billable or Non Billable'

Actions #5

Updated by Ananth Kumar about 2 months ago

The mentioned issue is not fixed, please refer the videos attached.

Actions #6

Updated by Arun Sundar 15 days ago

  • Status changed from New to Resolved
  • Assignee changed from Arun Sundar to Vengadeshwaran R
Actions #7

Updated by Arun Sundar 15 days ago

  • Status changed from Resolved to In Progress
  • Assignee changed from Vengadeshwaran R to Arun Sundar